Babysitter changeover-optimizer
Setup and changeover time reduction skill with SMED methodology and sequence optimization
install
source · Clone the upstream repo
git clone https://github.com/a5c-ai/babysitter
Claude Code · Install into ~/.claude/skills/
T=$(mktemp -d) && git clone --depth=1 https://github.com/a5c-ai/babysitter "$T" && mkdir -p ~/.claude/skills && cp -r "$T/library/specializations/domains/business/operations/skills/changeover-optimizer" ~/.claude/skills/a5c-ai-babysitter-changeover-optimizer && rm -rf "$T"
manifest:
library/specializations/domains/business/operations/skills/changeover-optimizer/SKILL.mdtags
source content
Changeover Optimizer
Overview
The Changeover Optimizer skill provides comprehensive capabilities for reducing setup and changeover times. It supports SMED (Single-Minute Exchange of Die) methodology, sequence optimization, and changeover time tracking.
Capabilities
- Internal/external setup separation
- Changeover video analysis
- Parallel task identification
- Standardization opportunities
- Quick-release mechanisms
- Sequence optimization
- Changeover matrix
- Time reduction tracking
Used By Processes
- LEAN-004: Kanban System Design
- CAP-002: Production Scheduling Optimization
- LEAN-003: Kaizen Event Facilitation
Tools and Libraries
- Video analysis tools
- SMED templates
- Time study software
- Scheduling optimization
Usage
skill: changeover-optimizer inputs: equipment: "Injection Molding Press 5" current_changeover_time: 120 # minutes target_changeover_time: 30 changeover_data: video_analysis: "changeover_video_url" task_breakdown: - task: "Remove old mold" time: 15 type: "internal" - task: "Get new mold from storage" time: 20 type: "internal" - task: "Install new mold" time: 25 type: "internal" - task: "Connect utilities" time: 15 type: "internal" - task: "Adjust parameters" time: 25 type: "internal" - task: "Run test shots" time: 20 type: "internal" outputs: - current_state_analysis - internal_external_separation - improvement_opportunities - optimized_procedure - changeover_matrix - implementation_plan
SMED Methodology
Stage 1: Separate Internal and External Setup
| Type | Definition | Goal |
|---|---|---|
| Internal | Must stop machine | Minimize |
| External | Machine running | Maximize |
Stage 2: Convert Internal to External
- Pre-stage tools and materials
- Pre-heat/pre-cool components
- Prepare documentation
- Pre-adjust settings
Stage 3: Streamline All Operations
- Parallel tasks (multiple operators)
- Eliminate adjustments
- Standardize procedures
- Use quick-release mechanisms
Changeover Analysis
Current State: - Total time: 120 minutes - Internal: 100 minutes - External: 20 minutes Improvement Opportunities: 1. Move mold retrieval to external: -20 min 2. Pre-heat mold: -10 min 3. Use quick-clamps: -15 min 4. Parallel connection work: -10 min 5. Eliminate test shots: -15 min Target State: - Total time: 30 minutes - Internal: 25 minutes - External: 35 minutes
Changeover Matrix
| From / To | Product A | Product B | Product C |
|---|---|---|---|
| Product A | - | 30 min | 45 min |
| Product B | 35 min | - | 25 min |
| Product C | 40 min | 30 min | - |
Quick Changeover Techniques
| Technique | Application |
|---|---|
| Quick-release clamps | Replace bolts |
| Intermediate jigs | Pre-positioned tooling |
| Color coding | Visual identification |
| One-turn fasteners | Reduce turns required |
| Standardized heights | Eliminate adjustments |
| Preset gauges | Eliminate measurement |
Implementation Steps
- Document current state (video)
- Separate internal/external
- Convert internal to external
- Streamline internal setup
- Streamline external setup
- Standardize and train
- Track and improve
Integration Points
- Production scheduling systems
- Video analysis tools
- Training platforms
- OEE tracking systems