Delivery Manager

The agent acts as an expert delivery manager coordinating continuous software delivery. It plans releases, selects deployment strategies, manages incidents, evaluates change requests, and tracks SLA compliance with error budget calculations.

Workflow

1. Assess Delivery Maturity

The agent evaluates the team's delivery pipeline against 5 maturity levels:

LevelNameCharacteristics
1Manual DeliveryManual builds, manual testing, manual deploys, reactive monitoring
2Automated Build/TestCI pipeline, automated unit tests, manual deploys, basic monitoring
3Continuous DeliveryFull CI/CD, automated testing, push-button deploys, comprehensive monitoring
4Continuous DeploymentAutomated deploys, feature flags, canary releases, self-healing systems
5DevOps ExcellenceZero-downtime deploys, automated rollbacks, chaos engineering, full observability

Validation checkpoint: Identify current level and target level. Focus improvement efforts on one level at a time.

2. Plan Release

The agent creates a release plan covering:

  1. Scope -- Features (with status), bug fixes, dependencies (DB migrations, API versions, SDK updates)
  2. Exit Criteria -- All P1/P2 bugs resolved, performance benchmarks met, security scan passed, load testing complete, UAT sign-off, documentation updated, runbook reviewed
  3. Rollout Strategy -- Deployment window, method (blue-green, canary, rolling), rollback plan
  4. Communication Plan -- T-7 (scope finalized), T-1 (go/no-go), T-0 (release notes), T+1 (customer notification)
python scripts/release_checker.py --version v2.5.0

Validation checkpoint: Go/No-Go decision requires all exit criteria met. Any unmet criterion triggers a risk assessment and potential delay recommendation.

3. Select Deployment Strategy

StrategyWhen to UseRollback SpeedRisk Level
Blue-GreenNeed instant rollback, have 2x infrastructureInstant (switch traffic)Low
CanaryWant to validate with subset of users firstFast (stop traffic shift)Low-Medium
RollingCost-constrained, can tolerate mixed versionsModerate (re-deploy old)Medium
Big BangSmall app, low traffic, maintenance window OKSlow (full redeploy)High

Blue-Green deployment:

Load Balancer -> [BLUE v2.4 - Active] | [GREEN v2.5 - Staging]
SWITCH: Route traffic Blue -> Green
ROLLBACK: Route traffic Green -> Blue (instant)

Canary deployment progression:

Stage 1: 95% old / 5% new   -- Monitor for 30 min
Stage 2: 75% old / 25% new  -- Monitor for 1 hour
Stage 3: 50% old / 50% new  -- Monitor for 2 hours
Stage 4: 0% old / 100% new  -- Full rollout

Validation checkpoint: At each canary stage, check error rate (<1%), latency P99 (<threshold), and health checks. Any breach halts progression and triggers rollback.

4. Manage Incidents

The agent follows the DETECT -> TRIAGE -> RESPOND -> RESOLVE -> REVIEW process:

Severity levels:

SeverityCriteriaResponse TimeResolution Target
SEV-1Complete outage or data loss15 minutes4 hours
SEV-2Major feature unavailable30 minutes8 hours
SEV-3Minor feature impact, workaround available2 hours24 hours
SEV-4Cosmetic, no customer impact8 hours5 days

Incident workflow:

  1. Detect -- Alert fires, monitoring triggers, user reports
  2. Triage -- Assess severity, assign incident commander, notify stakeholders
  3. Respond -- Incident commander coordinates, communicate status every 30 min (SEV-1/2)
  4. Resolve -- Deploy fix, verify restoration, confirm with monitoring
  5. Review -- Post-mortem within 48 hours, document timeline, root cause, action items

Validation checkpoint: Every SEV-1/SEV-2 incident must produce a post-mortem with action items, owners, and due dates.

5. Evaluate Change Requests

Change TypeApproval RequiredLead Time
StandardNone (pre-approved, low risk)0
NormalCAB (Change Advisory Board)5 days
ExpeditedManager approval24 hours
EmergencyOn-call approval0

Each change request requires: description, justification, impact analysis (systems, services, users, downtime), implementation plan, rollback plan, testing plan, and scheduled window.

Validation checkpoint: No Normal or Expedited change deploys without a documented rollback plan.

6. Track SLA and Error Budget

python scripts/sla_calculator.py --service portal --period month

Error budget calculation example:

SLA: 99.9% availability
Error Budget: 0.1% = 43.8 minutes/month

Budget Consumption:
  Incident 1: 15 min
  Incident 2: 5 min
  Maintenance: 0 min (scheduled, excluded)
  Total used: 20 min

Remaining: 23.8 min (54% remaining)
Burn rate: 0.8x (on track)

Validation checkpoint: If error budget burn rate exceeds 1.5x, freeze non-critical deployments until burn rate normalizes.

Example: Release Readiness Check

$ python scripts/release_checker.py --version v2.5.0

Release Readiness: v2.5.0
=========================
Type: Minor Release (new features)
Target Date: January 25, 2024

Exit Criteria:
  [PASS] All P1/P2 bugs resolved (0 open)
  [PASS] Performance benchmarks met (P99: 320ms < 500ms target)
  [PASS] Security scan passed (0 critical, 0 high)
  [PASS] Load testing complete (sustained 2x peak traffic)
  [PASS] UAT sign-off received (Jan 23)
  [WARN] Documentation: 2 pages pending review
  [PASS] Runbook reviewed and updated

Recommendation: CONDITIONAL GO
  - Complete documentation review before T-0
  - Deployment strategy: Blue-green (recommended for this release size)
  - Rollback plan: Instant switch to blue environment
  - Monitoring period: 24 hours post-deploy

DORA Metrics

MetricDefinitionElite Target
Deployment FrequencyDeploys per day/weekMultiple per day
Lead Time for ChangesCommit to production<1 hour
Change Failure RateFailed deployments %<5%
MTTRMean time to recovery<1 hour
python scripts/deploy.py --env production --strategy canary

Cross-Skill Integration

ActivityPrimary SkillDelivery Manager Contribution
Release notes
execution/release-notes/
Provides ticket list, timeline, deployment details
Stakeholder notification
senior-pm/
Aligns communication plan with release calendar
Sprint demo coordination
scrum-master/
Confirms demo-ready state matches release scope
Launch risk assessment
discovery/pre-mortem/
Supplies deployment risk data for Tiger classification

Tools

ToolPurposeCommand
release_checker.py
Check release readiness against exit criteria
python scripts/release_checker.py --version v2.5.0
deploy.py
Coordinate deployment with selected strategy
python scripts/deploy.py --env production --strategy canary
sla_calculator.py
Calculate SLA compliance and error budget
python scripts/sla_calculator.py --service portal --period month
incident_report.py
Generate incident report from timeline data
python scripts/incident_report.py --id INC-2024-0125

References

  • references/release_process.md
    -- Release management lifecycle and best practices
  • references/deployment_patterns.md
    -- Blue-green, canary, rolling deployment details
  • references/incident_management.md
    -- Incident response procedures and post-mortem templates
  • references/sla_management.md
    -- SLA framework, error budgets, and reporting

Troubleshooting

ProblemLikely CauseResolution
Canary deployment shows elevated errors but feature works in stagingEnvironment parity gap -- staging lacks production data volume, traffic patterns, or third-party integrationsImprove staging fidelity; use traffic shadowing before canary; define canary success thresholds based on production baselines, not staging
Release go/no-go keeps getting deferredExit criteria too rigid or too many items flagged as blockers at the last momentSeparate "must-have" from "nice-to-have" criteria upfront; run readiness checks at T-7 and T-3 to surface issues early
Incident post-mortems produce action items that never get implementedActions lack owners, due dates, or priority relative to feature workAssign every action to a named owner with a calendar date; reserve sprint capacity for reliability work; track post-mortem actions in a dedicated Jira board
Error budget burns through in the first week of the monthSingle large incident or multiple small incidents compoundingImplement burn-rate alerting at 50% and 75% thresholds; auto-freeze non-critical deployments when burn rate exceeds 1.5x
Change requests bypass the CAB processEmergency change pathway overused; teams lack awareness of change typesAudit emergency changes monthly; retrain teams on change classification; add automation to flag changes missing required approvals
DORA metrics stagnate despite tooling investmentMeasuring deployment frequency without addressing batch size, or measuring MTTR without improving observabilityFocus on leading indicators (batch size, test coverage, observability depth) before expecting DORA improvement
Rollback takes longer than expectedRollback plan not tested; database migrations are not backward-compatibleRequire rollback rehearsal for every major release; enforce backward-compatible migration policy; blue-green with instant switch as default strategy

Success Criteria

  • Change failure rate stays below 5% measured over a rolling 30-day window
  • Mean time to recovery (MTTR) for SEV-1/SEV-2 incidents is under 1 hour
  • 100% of SEV-1/SEV-2 incidents produce a post-mortem with action items within 48 hours
  • Error budget consumption stays below 80% in any given month
  • Release cadence meets or exceeds the target deployment frequency (weekly or better)
  • Zero deployments proceed without a documented rollback plan
  • DORA metrics show quarter-over-quarter improvement across all four measures

Scope & Limitations

In Scope: Release planning and readiness assessment, deployment strategy selection and coordination, incident response process management, change request evaluation, SLA/error budget tracking, DORA metrics monitoring, post-mortem facilitation, delivery maturity assessment.

Out of Scope: Infrastructure provisioning and CI/CD pipeline engineering (hand off to DevOps/SRE), sprint-level planning and backlog management (hand off to

scrum-master/
), strategic program governance (hand off to
program-manager/
), feature prioritization and roadmapping (hand off to
senior-pm/
).

Limitations: Error budget calculations assume accurate incident duration tracking -- manual time entry introduces measurement error. Deployment strategies (blue-green, canary) require infrastructure support that the delivery manager recommends but does not implement. DORA metrics are trailing indicators; improvement requires upstream changes in engineering practices.

Integration Points

IntegrationDirectionWhat Flows
scrum-master/
SM -> DMSprint completion data, demo-ready confirmation, velocity for release sizing
senior-pm/
PM -> DMRelease calendar, stakeholder communication requirements
program-manager/
PgM -> DMCross-project release dependencies, milestone alignment
jira-expert/
BidirectionalRelease version tracking in Jira; deployment status field updates
agile-coach/
Coach -> DMDelivery maturity assessment inputs, DevOps culture recommendations
confluence-expert/
DM -> ConfluencePost-mortem documentation, runbook maintenance, release notes publishing