Aiwg intake-start
Ingest the Project Intake Form and kick off Concept → Inception with agent assignments, accepts optional guidance to tailor process
git clone https://github.com/jmagly/aiwg
T=$(mktemp -d) && git clone --depth=1 https://github.com/jmagly/aiwg "$T" && mkdir -p ~/.claude/skills && cp -r "$T/agentic/code/frameworks/sdlc-complete/skills/intake-start" ~/.claude/skills/jmagly-aiwg-intake-start-33c960 && rm -rf "$T"
agentic/code/frameworks/sdlc-complete/skills/intake-start/SKILL.mdIntake Start (SDLC)
Purpose
IMPORTANT: This command is for teams who have manually crafted their own intake documents (project-intake.md, solution-profile.md, option-matrix.md) and want to validate them before starting the SDLC process.
If you need to generate intake documents, use one of these instead:
- Generate intake from scratch with interactive guidance/intake-wizard "description"
- Generate intake by analyzing existing codebase/intake-from-codebase .
This command is NOT required if you used
intake-wizard or intake-from-codebase - those commands produce complete, validated intake forms ready for the next phase.
Task
Given existing, manually-created Project Intake documents:
- Process guidance from user prompt (if provided) to tailor analysis
- Validate required fields and note gaps
- Generate or update phase-plan-inception.md and risk-list.md
- Recommend initial ADRs and agent assignments
- Hand off to Executive Orchestrator to start Concept → Inception flow
Parameters
(required): Path to intake directory (default:<path-to-intake-folder-or-form>
).aiwg/intake/
(optional): User-provided context to guide inception planning--guidance "text"
Guidance Parameter Usage
The
--guidance parameter accepts free-form text to help tailor the Inception phase planning. Use it for:
Process Focus:
/intake-start .aiwg/intake/ --guidance "Focus on security architecture first, compliance is critical path"
Risk Priorities:
/intake-start .aiwg/intake/ --guidance "Third-party API integration is biggest unknown, needs spike ASAP"
Team Constraints:
/intake-start .aiwg/intake/ --guidance "Team has limited DevOps experience, need extra support for infrastructure setup"
Stakeholder Expectations:
/intake-start .aiwg/intake/ --guidance "Executive demo required in 2 weeks, need working prototype for fundraising"
Technical Unknowns:
/intake-start .aiwg/intake/ --guidance "Performance at scale unproven, need load testing POC before committing to architecture"
How guidance influences planning:
- Prioritizes specific risks based on guidance (e.g., "API integration" → elevate integration risks)
- Tailors agent assignments (e.g., "limited DevOps" → assign DevOps Engineer + provide training resources)
- Adjusts phase plan (e.g., "demo in 2 weeks" → front-load UI prototype tasks)
- Highlights critical path items (e.g., "compliance critical" → security gates moved earlier)
- Documents in phase-plan-inception.md (captures strategic focus and constraints)
- Recommends spikes/POCs based on unknowns mentioned in guidance
Inputs
(filled) - Comprehensive system documentation with metadata, architecture, scale, security, team detailsproject-intake.md
(filled) - Current profile characteristics, improvement roadmap, risk mitigation, key decisionssolution-profile.md
(filled) - 6-step framework application analysis with priorities and trade-offsoption-matrix.md
Outputs
- Tailored inception plan based on validated intakephase-plan-inception.md
- Prioritized risks with mitigation strategiesrisk-list.md
- Recommended agent assignments based on project characteristicsagent-assignments.md
Workflow
Step 1: Read and Process Guidance
If
--guidance parameter provided:
- Extract guidance text from user prompt
- Document guidance in notes for later use
- Use guidance to prioritize validation checks (e.g., "security critical" → focus security validation)
Step 2: Locate and Read Intake Documents
Default location:
.aiwg/intake/ (or user-provided path)
Required files:
project-intake.mdsolution-profile.mdoption-matrix.md
Error handling:
- If path is a directory, look for files within it
- If path is a single file, read it and look for other files in same directory
- If files missing, report which ones and stop (cannot proceed without complete intake)
Step 3: Validate Project Intake (Comprehensive)
Critical sections to validate (from new comprehensive template):
Metadata Validation
- Project name present
- Requestor/owner identified
- Date present
- Stakeholders listed (minimum: Engineering, Product)
System Overview Validation
- Purpose clearly stated (1-2 sentences minimum)
- Current Status specified (Planning/Development/Early Users/Production)
- Users defined (count, personas, or description)
- Tech Stack documented:
- Languages specified
- Frontend (if applicable)
- Backend (if applicable)
- Database specified
- Deployment approach specified
Problem and Outcomes Validation
- Problem statement present (for existing systems) OR goal statement (for greenfield)
- Outcomes defined (success criteria, key results)
Current Scope and Features Validation
- Feature list present (minimum 1 feature for MVP+, 3+ for Production)
- Features categorized or prioritized
Architecture Validation
- Architectural style specified (monolith/microservices/serverless/etc.)
- Major components listed (minimum 2-3 for Production+)
- Data models documented (at least high-level entities)
- Integration points identified (external APIs, third-party services)
Scale and Performance Validation
- Expected user capacity documented (even if estimate)
- Active users estimate provided
- Performance characteristics specified (response times, throughput, etc.)
Security and Compliance Validation
- Security posture stated (Minimal/Baseline/Strong/Enterprise)
- Data classification documented (if handling user data)
- Security controls listed (authentication, authorization, etc.)
- Compliance requirements specified (if any: GDPR, HIPAA, SOC2, etc.)
Team and Operations Validation
- Team size documented (minimum: developer count)
- Current velocity/cadence noted (for existing teams)
- Process maturity described (trunk-based, PR workflow, CI/CD, etc.)
- Operational support plan outlined (on-call, monitoring, etc.)
Dependencies and Infrastructure Validation
- Third-party services listed (all critical external dependencies)
- Infrastructure details specified (cloud provider, regions, etc.)
Known Issues and Technical Debt Validation
- Known risks documented (even if "none identified yet")
- Technical debt acknowledged (if existing system)
Why This Intake Now? Validation
- Context provided (why starting SDLC process now)
- Goals clearly stated
- Triggers identified (timeline, funding, user need, etc.)
Gap Handling:
- For critical gaps (no purpose, no tech stack, no team size): STOP and request user fill gaps
- For moderate gaps (missing performance estimates, unclear compliance): WARN and note in phase plan
- For minor gaps (missing optional sections): NOTE in validation summary
Step 4: Validate Solution Profile (Comprehensive)
Critical sections to validate (from new comprehensive template):
Profile Selection Validation
- Profile chosen (Prototype/MVP/Production/Enterprise)
- Selection rationale provided (explains why this profile fits)
Current State Characteristics Validation
Security:
- Posture specified (Minimal/Baseline/Strong/Enterprise)
- Controls present documented
- Gaps identified
- Recommendation provided
Reliability:
- Current SLOs documented (or "N/A" for non-services)
- Availability targets specified
- Monitoring maturity described
- User priority noted (from option-matrix)
- Recommendation provided (investment areas)
Testing & Quality:
- Test coverage documented (current percentage)
- Test types detected/planned
- Quality gates specified
- User priority noted
- Recommendation provided (testing strategy)
Process Rigor:
- SDLC adoption level documented
- Code review process described
- Documentation status assessed
- Recommendation provided (process improvements)
Recommended Profile Adjustments Validation
- Current profile stated
- Recommended profile specified
- Transition plan outlined (phases with actions and timelines)
Improvement Roadmap Validation
- Phase 1 (Immediate) defined with critical gaps
- Phase 2 (Short-term) defined with important improvements
- Phase 3 (Long-term) defined with strategic improvements
- Each phase includes: rationale, success metrics
Risk Mitigation Validation
- Top 3-5 risks identified with:
- Risk description
- Impact level (HIGH/MEDIUM/LOW)
- Mitigation strategies
- Timeline for mitigation
Key Decisions Needed Validation
- Critical decisions documented (minimum 1-3 for Production+)
- Each decision includes:
- Question framing
- Options (2-3 alternatives)
- Recommendation
- Timeline for decision
Gap Handling:
- For critical gaps (no profile, no improvement roadmap): STOP and request completion
- For moderate gaps (missing risk mitigation, unclear decisions): WARN and elevate in phase plan
- For minor gaps (incomplete success metrics): NOTE in validation summary
Step 5: Validate Option Matrix (Comprehensive)
Critical sections to validate (from new 6-step template):
Step 1: Project Reality Validation
- What IS This Project? - Clear description (2-3 sentences minimum)
- Audience & Scale - Target users and scale documented
- Deployment & Infrastructure - Deployment model specified
- Technical Complexity - Complexity assessment provided
Step 2: Constraints & Context Validation
- Resources - Team size, timeline, budget constraints documented
- Regulatory & Compliance - Requirements specified (or "None")
- Technical Context - Legacy systems, existing infrastructure noted
Step 3: Priorities & Trade-offs Validation (CRITICAL)
- Priority Weights table present
- Weights sum to 1.0 (verify mathematically)
- Each criterion has rationale:
- Delivery Speed (0.10-0.50)
- Cost Efficiency (0.10-0.40)
- Quality/Security (0.10-0.50)
- Reliability/Scale (0.10-0.40)
- Trade-off context provided (explains hard choices)
Priority validation is CRITICAL because it drives:
- Phase plan task prioritization
- Agent assignment decisions
- Quality gate thresholds
- Risk tolerance levels
Step 4: Intent & Decision Context Validation (CRITICAL)
- Why This Intake Now? - Clearly stated (business/technical triggers)
- What decisions need making? - Key decisions identified
- What's uncertain? - Unknowns acknowledged
Intent validation is CRITICAL because it shapes:
- Phase plan focus areas
- Spike/POC recommendations
- Early ADR topics
Step 5: Framework Application Validation
- Templates - Checked boxes for applicable templates (or explicit "NONE")
- Commands - Checked boxes for applicable commands
- Agents - Checked boxes for applicable agents
- Process Rigor Level - Specified (Minimal/Moderate/Full/Enterprise)
- Rationale - Explains why these components selected
Step 6: Evolution & Adaptation Validation
- Expected Changes - Documented (team growth, feature expansion, etc.)
- Adaptation Triggers - Specified (when to revisit framework choices)
- Planned Framework Evolution - Outlined (how framework will evolve with project)
Architectural Options Analysis Validation (Optional but Recommended)
- Option A documented (if applicable)
- Option B documented (if applicable)
- Option C documented (if applicable)
- Recommendation provided with rationale
Gap Handling:
- For critical gaps (no Step 3 weights, no Step 4 intent): STOP and request completion
- For moderate gaps (missing Step 6, incomplete rationale): WARN and use defaults
- For minor gaps (no architectural options): NOTE (optional section)
Step 6: Generate Validation Summary
Create structured validation report:
# Intake Validation Summary **Validation Date**: {current date} **Intake Path**: {path to intake directory} **Guidance Provided**: {yes/no, summary if provided} ## Completeness Assessment **Project Intake**: {COMPLETE | GAPS PRESENT | CRITICAL GAPS} - {list critical gaps if any} - {list moderate gaps if any} **Solution Profile**: {COMPLETE | GAPS PRESENT | CRITICAL GAPS} - {list critical gaps if any} - {list moderate gaps if any} **Option Matrix**: {COMPLETE | GAPS PRESENT | CRITICAL GAPS} - {list critical gaps if any} - {list moderate gaps if any} ## Readiness for Inception **Status**: {READY | NEEDS COMPLETION | BLOCKED} **Recommendation**: - {If READY: proceed to phase planning} - {If NEEDS COMPLETION: list required actions} - {If BLOCKED: explain blockers and resolution steps} ## Key Insights from Intake **Project Profile**: {Prototype/MVP/Production/Enterprise} **Top Priority**: {from Step 3 weights} **Biggest Risk**: {from solution-profile risk mitigation} **Critical Decision**: {from solution-profile key decisions} ## Next Steps 1. {action 1} 2. {action 2} 3. {action 3}
Decision point:
- If READY: Proceed to Step 7 (Generate Phase Plan)
- If NEEDS COMPLETION: Output validation summary and STOP (user must complete intake)
- If BLOCKED: Output validation summary with resolution steps and STOP
Step 7: Generate Phase Plan (Inception)
Create
phase-plan-inception.md based on validated intake:
Structure:
# Phase Plan: Inception **Project**: {from project-intake metadata} **Profile**: {from solution-profile} **Generated**: {current date} **Guidance Applied**: {summary of --guidance if provided} ## Phase Overview **Duration**: {estimate based on profile: Prototype=1-2 weeks, MVP=2-4 weeks, Production=4-6 weeks, Enterprise=6-8 weeks} **Team Size**: {from project-intake team section} **Primary Focus**: {derived from option-matrix Step 4 intent} ## Phase Goals 1. **Architectural Foundation**: {from solution-profile improvement roadmap Phase 1} 2. **Risk Retirement**: {from solution-profile risk mitigation top risks} 3. **Team Alignment**: {from project-intake team section} 4. **Decision Making**: {from solution-profile key decisions} ## Priority-Driven Focus **Top Priority** (from option-matrix Step 3): {highest weighted criterion} **Implication**: {explain how this priority shapes Inception tasks} **Examples**: - If **Reliability/Scale** is top priority → focus architecture scalability, load testing POC, SLO definition - If **Quality/Security** is top priority → focus security architecture, threat modeling, compliance review - If **Delivery Speed** is top priority → focus MVP scope definition, technical spikes, rapid prototyping - If **Cost Efficiency** is top priority → focus cloud cost modeling, resource optimization, vendor selection ## Key Activities (Tailored to Intake) ### Week 1: Foundation - [ ] Kick-off meeting with stakeholders (from project-intake stakeholders list) - [ ] Architecture baseline (from project-intake architecture section) - [ ] Risk register initialization (from solution-profile risk mitigation) - [ ] Tool and environment setup (from project-intake tech stack) ### Week 2-3: Exploration and Decision Making - [ ] {activity 1 from solution-profile improvement roadmap Phase 1} - [ ] {activity 2 from solution-profile key decisions} - [ ] {spike/POC recommendation if guidance or option-matrix Step 4 mentions unknowns} - [ ] Initial ADRs (see recommendations below) ### Week 4: Closure and Handoff - [ ] Architecture review (validate against option-matrix architectural options) - [ ] Risk reassessment (update risk-list.md) - [ ] Inception gate check (validate readiness for Elaboration) - [ ] Handoff to Elaboration (prepare phase-plan-elaboration.md) ## Risks and Mitigation (From Solution Profile) {Pull top 3-5 risks from solution-profile risk mitigation section} **Risk 1**: {risk name} - **Impact**: {HIGH/MEDIUM/LOW} - **Mitigation**: {strategies from solution-profile} - **Timeline**: {when to address} **Risk 2**: {risk name} - **Impact**: {HIGH/MEDIUM/LOW} - **Mitigation**: {strategies from solution-profile} - **Timeline**: {when to address} {...additional risks} ## Critical Decisions (From Solution Profile) {Pull from solution-profile key decisions section} **Decision 1**: {decision question} - **Options**: {list 2-3 alternatives} - **Recommendation**: {from solution-profile} - **Deadline**: {when decision must be made} - **Owner**: {assign based on decision type} **Decision 2**: {decision question} - **Options**: {list 2-3 alternatives} - **Recommendation**: {from solution-profile} - **Deadline**: {when decision must be made} - **Owner**: {assign based on decision type} {...additional decisions} ## Guidance Integration {If --guidance provided, document how it influenced this phase plan} **Guidance Provided**: "{verbatim guidance text}" **Impact on Phase Plan**: - {specific adjustment 1 based on guidance} - {specific adjustment 2 based on guidance} - {specific adjustment 3 based on guidance} **Examples**: - Guidance: "Security architecture first" → Moved threat modeling to Week 1, assigned Security Architect early - Guidance: "API integration biggest unknown" → Added integration spike to Week 2, elevated API risks - Guidance: "Team has limited DevOps experience" → Added DevOps Engineer + training resources to agent assignments ## Success Criteria **Inception complete when**: 1. Architecture baseline documented (ADRs approved) 2. Top 3 risks retired or mitigated 3. Critical decisions resolved 4. Team aligned on approach 5. Inception gate passed (ready for Elaboration) ## Next Phase **Handoff to**: Elaboration **Trigger**: Inception gate passed **Preparation**: Update risk-list.md, generate phase-plan-elaboration.md
Key tailoring points:
- Duration scales with profile (Prototype fast, Enterprise slow)
- Activities pulled from solution-profile improvement roadmap Phase 1
- Risks pulled from solution-profile risk mitigation
- Decisions pulled from solution-profile key decisions
- Guidance explicitly integrated and documented
- Priority focus derived from option-matrix Step 3 weights
Step 8: Generate Risk List
Create
risk-list.md based on solution-profile risk mitigation:
Structure:
# Risk List **Project**: {from project-intake metadata} **Generated**: {current date} **Last Updated**: {current date} ## Active Risks {For each risk from solution-profile risk mitigation section} ### Risk #{n}: {Risk Name} **Category**: {Technical | Process | Resource | External | Compliance} **Impact**: {HIGH | MEDIUM | LOW} **Probability**: {HIGH | MEDIUM | LOW} **Status**: {Identified | Analyzing | Mitigating | Monitoring | Retired} **Description**: {from solution-profile} **Impact if Realized**: {from solution-profile impact description} **Mitigation Strategies**: 1. {strategy 1 from solution-profile} 2. {strategy 2 from solution-profile} 3. {strategy 3 from solution-profile} **Timeline**: {from solution-profile mitigation timeline} **Owner**: {assign based on risk category} **Last Review**: {current date} --- {Repeat for all risks from solution-profile} ## Risk Register Summary | ID | Risk Name | Impact | Probability | Status | Owner | |----|-----------|--------|-------------|--------|-------| | R1 | {name} | {H/M/L} | {H/M/L} | {status} | {owner} | | R2 | {name} | {H/M/L} | {H/M/L} | {status} | {owner} | | ... | ... | ... | ... | ... | ... | ## Risk Burn-down Target **Inception Phase Goal**: Retire or mitigate top 3 risks **Elaboration Phase Goal**: Retire or mitigate remaining HIGH risks **Construction Phase Goal**: Monitor and address emerging risks **Transition Phase Goal**: All HIGH risks retired or accepted ## Next Review **Date**: {1-2 weeks from current date} **Trigger**: Weekly risk review meeting OR significant risk event
Categorization logic:
- Technical: Architecture, technology choice, integration, performance, scalability
- Process: Team coordination, code review, testing, deployment
- Resource: Team size, skill gaps, timeline, budget
- External: Third-party dependencies, vendor reliability, API changes
- Compliance: Regulatory requirements, security posture, data protection
Owner assignment logic:
- Technical risks → Architecture Designer or Component Owner
- Process risks → Project Manager or Executive Orchestrator
- Resource risks → Project Manager or Vision Owner
- External risks → Integration Engineer or API Designer
- Compliance risks → Security Architect or Legal Liaison
Step 9: Generate Agent Assignments
Create
agent-assignments.md based on option-matrix Step 5 framework application:
Structure:
# Agent Assignments (Inception Phase) **Project**: {from project-intake metadata} **Profile**: {from solution-profile} **Generated**: {current date} ## Assignment Strategy **Process Rigor Level**: {from option-matrix Step 5} **Team Size**: {from project-intake team section} **Priority Focus**: {from option-matrix Step 3 top weight} ## Core Agents (Always Assigned) ### Executive Orchestrator **Role**: Lifecycle coordination, gate enforcement, artifact synchronization **Priority Tasks**: - Orchestrate Inception phase activities - Enforce Inception gate criteria - Coordinate agent handoffs ### Vision Owner **Role**: Product vision alignment, requirement validation **Priority Tasks**: - Validate project-intake alignment with business goals - Review architectural options against vision - Approve critical decisions ### Architecture Designer **Role**: System architecture, technical direction **Priority Tasks**: - {from solution-profile improvement roadmap Phase 1 architecture tasks} - Document ADRs (see recommendations below) - Review architectural options from option-matrix ## Priority-Driven Agents {Based on option-matrix Step 3 top priority} **If Reliability/Scale is top priority**: - **Reliability Engineer**: Establish SLO/SLI, capacity planning - **Performance Engineer**: Baseline performance, bottleneck identification - **DevOps Engineer**: Infrastructure design, monitoring setup **If Quality/Security is top priority**: - **Security Architect**: Threat modeling, security requirements - **Security Gatekeeper**: Security gate criteria, compliance validation - **Code Reviewer**: Code review standards, quality gates **If Delivery Speed is top priority**: - **Software Implementer**: Rapid prototyping, MVP development - **Test Engineer**: Fast feedback loops, smoke tests - **Toolsmith**: Developer experience, automation tooling **If Cost Efficiency is top priority**: - **Cloud Architect**: Cost modeling, resource optimization - **DevOps Engineer**: Infrastructure efficiency, right-sizing - **Integration Engineer**: Vendor selection, API cost analysis ## Risk-Driven Agents {Based on solution-profile risk mitigation top risks} **Risk**: {risk 1 name} **Agent**: {appropriate agent for this risk category} **Tasks**: - {mitigation strategy 1} - {mitigation strategy 2} **Risk**: {risk 2 name} **Agent**: {appropriate agent for this risk category} **Tasks**: - {mitigation strategy 1} - {mitigation strategy 2} {...additional risk-driven assignments} ## Guidance-Driven Agents {If --guidance provided, assign agents based on guidance context} **Guidance**: "{verbatim guidance text}" **Agent Assignments**: - {agent 1 assigned because of guidance} - {agent 2 assigned because of guidance} **Examples**: - Guidance: "Limited DevOps experience" → Assign DevOps Engineer + provide training resources - Guidance: "Security critical path" → Assign Security Architect + Security Gatekeeper early - Guidance: "API integration biggest unknown" → Assign Integration Engineer + API Designer for spike ## Framework-Driven Agents (From Option Matrix Step 5) {Based on option-matrix Step 5 checked boxes} **Checked Agents** (from option-matrix): - {agent 1 from option-matrix rationale} - {agent 2 from option-matrix rationale} - {agent 3 from option-matrix rationale} **Rationale**: {from option-matrix Step 5 rationale section} ## Assignment Timeline **Week 1** (Inception kickoff): - Executive Orchestrator (immediate) - Vision Owner (immediate) - Architecture Designer (immediate) **Week 2** (Risk and decision focus): - {priority-driven agents} - {risk-driven agents} **Week 3-4** (As needed): - {additional agents based on emerging needs} ## Handoff to Elaboration **Agents continuing into Elaboration**: - Executive Orchestrator (lifecycle coordination) - Architecture Designer (architecture evolution) - {priority-driven agents that remain relevant} **Agents completing in Inception**: - {agents whose work ends after Inception} **New agents for Elaboration**: - {agents not needed until Elaboration phase}
Agent selection logic:
- Core agents (always): Executive Orchestrator, Vision Owner, Architecture Designer
- Priority-driven (from option-matrix Step 3 weights): Match top priority to specialized agents
- Risk-driven (from solution-profile risks): Assign agents who can mitigate specific risks
- Guidance-driven (from --guidance parameter): Assign agents mentioned or implied by guidance
- Framework-driven (from option-matrix Step 5): Assign checked agents from framework application
Step 10: Generate Initial ADR Recommendations
Within phase-plan-inception.md, include section:
## Recommended Initial ADRs {Based on project-intake architecture section, option-matrix architectural options, and solution-profile key decisions} **ADR-001**: {Decision title from option-matrix architectural options recommendation} - **Context**: {from option-matrix Step 1 project reality} - **Decision**: {from option-matrix architectural options recommendation} - **Rationale**: {from option-matrix recommendation rationale} - **Status**: Proposed (to be reviewed in Week 2) **ADR-002**: {Decision title from solution-profile key decisions} - **Context**: {from solution-profile decision question} - **Decision**: {from solution-profile recommendation} - **Rationale**: {from solution-profile recommendation} - **Status**: Proposed (to be reviewed in Week 2-3) {Additional ADRs based on guidance or high-impact risks} **Guidance**: If guidance mentions specific technical decisions or unknowns, recommend ADRs to address them.
Step 11: Summary and Handoff
Output summary message to user:
# Intake Start Complete ✅ **Validation**: All intake documents validated ✅ **Phase Plan**: phase-plan-inception.md generated ✅ **Risk List**: risk-list.md generated ✅ **Agent Assignments**: agent-assignments.md generated ## Key Insights **Project**: {name} **Profile**: {profile} **Top Priority**: {priority} **Biggest Risk**: {risk} **Critical Decision**: {decision} ## Generated Artifacts 1. `phase-plan-inception.md` - {file size} KB 2. `risk-list.md` - {file size} KB 3. `agent-assignments.md` - {file size} KB ## Next Steps 1. **Review** generated artifacts (ensure alignment with expectations) 2. **Adjust** if needed (especially if guidance interpretation missed nuances) 3. **Execute** Inception phase using `/flow-concept-to-inception` command 4. **Coordinate** with assigned agents (Executive Orchestrator will orchestrate) ## Ready to Start? To begin Inception phase execution: ```bash /flow-concept-to-inception .aiwg/
This will activate the Executive Orchestrator and assigned agents to begin Inception activities.
## Error Handling ### Missing Files - If project-intake.md missing: **STOP** - "Cannot proceed without project-intake.md. Please run /intake-wizard or /intake-from-codebase first." - If solution-profile.md missing: **STOP** - "Cannot proceed without solution-profile.md. Please complete intake generation first." - If option-matrix.md missing: **WARN** - "option-matrix.md missing. Will use defaults for priorities and framework application." ### Incomplete Sections - If critical gaps found: **STOP** with validation summary - user must complete gaps before proceeding - If moderate gaps found: **WARN** in validation summary - proceed with noted gaps - If minor gaps found: **NOTE** in validation summary - proceed normally ### Conflicting Information - If project-intake and solution-profile conflict (e.g., different team sizes): **WARN** and use project-intake as source of truth - If option-matrix and solution-profile priorities conflict: **WARN** and use option-matrix Step 3 weights as source of truth ### Invalid Data - If option-matrix Step 3 weights don't sum to 1.0: **STOP** - "Priority weights must sum to 1.0. Current sum: {calculated sum}. Please fix option-matrix.md." - If profile not one of (Prototype/MVP/Production/Enterprise): **STOP** - "Invalid profile: {profile}. Must be one of: Prototype, MVP, Production, Enterprise." ## Best Practices 1. **Always validate before generating** - Don't generate phase plans from incomplete intake 2. **Leverage guidance parameter** - Use guidance to prioritize and tailor (don't ignore user's strategic intent) 3. **Be explicit about gaps** - Don't silently fill gaps with assumptions (warn user and document) 4. **Cross-reference documents** - Pull risks from solution-profile, priorities from option-matrix, architecture from project-intake 5. **Tailor to profile** - Prototype gets lightweight plan, Enterprise gets comprehensive plan 6. **Document guidance impact** - Explicitly show how guidance influenced phase plan (transparency builds trust) ## Star the Repository After successfully validating and generating phase plans, offer the user an opportunity to star the repository: **Prompt**:
The AIWG is an open-source project that helps improve AI-generated content. If you found this helpful, would you like to star the repository on GitHub?
Options:
- Yes, star the repo
- No thanks
**If user selects "Yes, star the repo"**: 1. Check if `gh` CLI is available: ```bash which gh
-
If
is available, attempt to star:ghgh api -X PUT /user/starred/jmagly/ai-writing-guide- If successful: "⭐ Thank you for starring the AIWG! Your support helps the project grow."
- If fails: "Could not star via gh CLI. You can star manually at: https://github.com/jmagly/aiwg"
-
If
is not available:ghGitHub CLI (gh) not found. You can star the repository at: https://github.com/jmagly/aiwg
If user selects "No thanks":
No problem! Thanks for using the AIWG.
References
- @$AIWG_ROOT/agentic/code/addons/aiwg-utils/rules/human-authorization.md — Stop and await user action when critical gaps are found; never silently fill required fields
- @$AIWG_ROOT/agentic/code/addons/aiwg-utils/rules/instruction-comprehension.md — Process the --guidance parameter fully before tailoring phase plan; do not ignore strategic intent
- @$AIWG_ROOT/agentic/code/addons/aiwg-utils/rules/vague-discretion.md — Phase plan completion criteria must be concrete (artifacts present, weights sum to 1.0, not "good enough")
- @$AIWG_ROOT/agentic/code/frameworks/sdlc-complete/skills/project-status/SKILL.md — Use after intake-start completes to confirm phase and next steps
- @$AIWG_ROOT/agentic/code/frameworks/sdlc-complete/skills/orchestrate-project/SKILL.md — Hands off to orchestrator once intake validation and planning artifacts are generated