generate-project-plan

Language Detection

Determine the language of the user's request:

  • If the request is in Russian → use templates with
    -ru
    suffix
  • Otherwise → use templates with
    -en
    suffix

All output (headings, labels, comments, instructions) must match the detected language.

Triggers

Russian: «сформируй план проекта», «подготовь план», «составь project plan», «нужен план проекта» English: "generate project plan", "create project plan", "build plan", "prepare project plan"


1. Inputs

DataRequiredSourceNotes
Project charter (project-charter.md)yesknowledge or chatApproved charter. Extract: goal, scope, dates, budget (if present), team, constraints, top-3 risks
Duration estimatesnochat or knowledgeWork package estimates from the user. If absent — agent estimates and marks as assumption
Team availability datanochat or knowledgeLoad by period, constraints (vacations, part-time). If absent — agent distributes evenly, marks as assumption
Additional inputsnochatPriorities, external dependencies, technical constraints not included in the charter

If no charter is available — request it (system-prompt-draft.md §3 p.2):

A project plan requires an approved charter (project-charter.md).
Available data: [list what is available].
Charter status: [not started / draft / approved].
If the charter has not been created yet — start with generate-charter.

2. Execution Algorithm

  1. Validate inputs. Check for an approved charter. Not found → request per §1 template. Do NOT generate a plan without a charter — this breaks the dependency chain. Found → step 2.
  2. Extract data from the charter. Break down by category: goal, scope (included/excluded), dates (start/end), budget (if specified), team, constraints, risks. Record gaps.
  3. Check data for conflicts. If charter dates conflict with user-provided duration estimates — do NOT resolve independently. List discrepancies, ask which takes precedence. Exception: if the user explicitly clarifies in chat — use the clarification.
  4. Decompose scope into work packages (WP). Each deliverable from the charter's "Included" section → one or more WPs. Granularity: a WP is a group of related tasks with a single output. Do NOT decompose to individual tasks — that is Jira level. Assign each WP an ID (WP-001, WP-002, etc.). Group WPs by project phase. After decomposition, count total WPs: if >20 — consolidate adjacent packages within the same phase. WP count must be ≤ 20 for MVP. If consolidation would lose meaning — record as assumption and proceed to step 5.
  5. Set duration for each WP.
    • Use user-provided estimates if available.
    • If no estimates — assess based on: scope volume, resource count, comparable projects, charter constraints. Mark each such estimate as assumption.
    • Unit: project ≤ 3 months → working days (wd); project > 3 months → weeks (wk). Unit must be consistent within one plan. 1 wk = 5 wd.
    • Verify: sum of critical path durations (accounting for maximum parallelism) ≤ total project duration from charter. If it doesn't fit — record as issue, propose options (parallel execution / scope reduction / resource increase / date shift). Do NOT generate WP dates beyond the charter end_date. If unavoidable — mark affected WPs with
      [⚠ exceeds deadline]
      and require a decision from the user before finalizing.
  6. Identify dependencies between WPs. For each related WP pair: dependency type (FS / SS / FF). FS is the default if the relationship is not explicit. Verify no circular dependencies.
  7. Define milestones. A milestone is a checkpoint marking the achievement of a significant result. A milestone is NOT a task — it has zero duration. It answers "what must be done by this point", not "what needs to be done". What counts as a milestone: phase completion (all WPs in phase closed); delivery of a key deliverable to the customer; external event the project depends on (approval, procurement, integration); go/no-go decision point. What does NOT count as a milestone: completion of a routine WP that is not a deliverable; internal intermediate results without external review; recurring events (weekly status, sprint reviews). Milestones from the charter (section 3) — must be included. ID: M1, M2, etc. Minimum: 3 milestones (start, mid, finish). Maximum: one per phase + key deliverables.
  8. Fill the resource map.
    • Use availability data if provided.
    • If not — take team from charter (section 5), distribute across WPs by role, treat load as uniform. Mark as assumption.
    • Period columns — actual project months (not fixed).
  9. Read the template
    project-plan-ru.md
    (or
    project-plan-en.md
    ) from project knowledge.
  10. Fill the template per the rules in section 3.
  11. Validate the output using the checklist (section 5).
  12. Present the output in chat. Format (system-prompt-draft.md §3 p.4):
    • What was done: "Project plan generated based on [list sources]."
    • Assumptions: list all (duration estimates, resource allocation, etc.).
    • Issues: if found (schedule overrun, insufficient resources).
    • What is required: "Approve, provide comments, or reject."
    • Do not include system paths. Use file name only: "Plan saved as project-plan.md."
  13. Wait for user response (system-prompt-draft.md §3 p.5).
    • Approval → generate final version.
    • Comments → revise, show updated version. After 3rd iteration — ask: "Continue revising or finalize the current version?"
  14. After approval:
    • Propose text for the user to insert into log.md and project-state.md (system-prompt-draft.md §11).
    • Notify: "Project plan approved. The following tasks are now available (can run in parallel): generate-risk-register (detailed risk register) and generate-comm-plan (communications plan). Which one to start?" (system-prompt-draft.md §7).

3. Section Fill Rules

Header Metadata

  • Version
    : 1.0
  • Date
    : current generation date.
  • File
    :
    project-plan.md
  • Document status
    :
    draft
    (on generation). After approval —
    approved
    .
  • Source
    : list documents used to generate the plan.

"Project Summary" Section

  • Fill from the charter. Fields
    Project goal
    ,
    Dates
    ,
    Team
    ,
    Customer
    ,
    PM
    — required.
  • Project goal
    — from charter section 1 (verbatim or condensed).
  • Dates
    — start_date and end_date from charter; duration — calculate.
  • Budget
    — from charter section 4 (total amount). If not specified — enter: "not defined". The plan is generated without budget data. This does not block generation.
  • Team
    — headcount from charter section 5.
  • Customer
    and
    PM
    — from charter sections 5/8.

"Phases and Work Packages" Section

Table is the core of the plan.

ColumnRule
IDUnique code: WP-001, WP-002, etc. Sequential numbering
PhasePhase name (Initiation, Planning, Development, etc.). Group WPs by phase
Work packageGroup of related tasks with a single output. NOT an individual task — task-level detail belongs in Jira
OwnerRole or name from charter team
DurationUnit selected by project duration: ≤ 3 months → working days (wd); > 3 months → weeks (wk). Consistent unit throughout the plan. Use suffix: "5 wd" or "2 wk". Calculation: 1 wk = 5 wd
Start / EndYYYY-MM-DD. Calculate from dependencies and duration. First WP start ≥ charter start_date. Last WP end ≤ charter end_date
DependenciesIDs of predecessor work packages. "—" if none
  • Minimum WPs: one per deliverable from the charter.
  • Maximum WPs: no more than 20 for MVP. Consolidate if exceeded.

"Milestones" Section

ColumnRule
IDM1, M2, etc.
MilestoneCheckpoint — event marking the achievement of a significant result. Zero duration
DateYYYY-MM-DD. Matches the end date of the corresponding WP or phase
Completion criterionSpecific, verifiable condition. Format: "[artifact/result] [action] [by whom]". Example: "Prototype accepted by customer", "API deployed to staging and passed smoke tests"
StatusOn generation:
not achieved
. Allowed values:
not achieved
/
achieved
/
overdue

"Dependencies" Section

Table details the relationships from the WP table's Dependencies column.

ColumnRule
Source blockID of WP that must finish/start
Target blockID of WP that depends on the source
TypeFS (Finish-to-Start) — default; SS (Start-to-Start); FF (Finish-to-Finish)
CommentExplanation of the relationship. Required for SS and FF types
  • Verify: no circular dependencies (A→B→C→A).
  • Every dependency from the WP table must appear here.

"Assumptions and Constraints" Section

  • Assumptions: all agent assumptions (duration estimates, resource allocation, priorities). One item per line.
  • Constraints: from charter (section 6) + identified during planning.

"Resource Map" Section

ColumnRule
Team memberName from team roster
RoleRole from charter
Period columnsProject months (adapt to actual dates). Load in % of full working time
Constraints / NotesVacations, part-time, outsourcing, dual roles
  • Use provided load data if available.
  • If not — distribute evenly across WPs, mark as assumption.
  • Total load per person per period must not exceed 100% (record as issue if exceeded).

4. Placeholder Table

Placeholders

{{}}
in the template are fill-in guides, not auto-substitution variables. Replace each with the corresponding value from the inputs.

PlaceholderRequiredSourceAllowed values
{{project_name}}
yeschartertext
{{version}}
yesagent"1.0" on creation
{{date}}
yessystemYYYY-MM-DD
{{doc_status}}
yesagentdraft / pending approval / approved / revision
{{source_docs}}
yesagentlist of input documents
{{project_goal}}
yescharter, section 1text
{{start_date}}
yescharter, section 3YYYY-MM-DD
{{end_date}}
yescharter, section 3YYYY-MM-DD
{{duration}}
yesagent (calculate)"N weeks" or "N months"
{{budget}}
nocharter, section 4number + currency or "not defined"
{{team_size}}
yescharter, section 5number
{{customer}}
yescharter, sections 5/8name
{{pm}}
yescharter, sections 5/8name
{{phase_name}}
yes (≥1)agentproject phase name
{{work_package}}
yes (≥1)agent / scopework package description
{{owner}}
yescharter / teamrole or name
{{wp_duration}}
yesuser / assumptionnumber + "wd" or "wk"
{{wp_start}}
yesagent (calculate)YYYY-MM-DD
{{wp_end}}
yesagent (calculate)YYYY-MM-DD
{{wp_dependency}}
noagentWP ID or "—"
{{milestone_name}}
yes (≥3)charter + agentmilestone name
{{done_criteria}}
yesagentcompletion condition: "[result] [action] [by whom]"
{{assumption_N}}
noagentassumption text
{{constraint_N}}
yes (≥1)charterconstraint text
{{name_N}}
nocharter / teamteam member name
{{role_N}}
nocharter / teamrole
{{load_period}}
nodata / assumptionnumber (% load)

5. Validation Checklist

Before presenting the output to the user — verify:

  • Charter used as primary source (no fabricated data)
  • All required placeholders replaced with values
  • No
    {{}}
    placeholders remain in the text
  • Every deliverable from the charter is covered by at least one WP
  • Dates are consistent: start_date ≤ WP dates ≤ end_date
  • No circular dependencies between WPs
  • Charter milestones included; milestone dates match the end of corresponding WPs/phases
  • Each milestone meets the criteria from §2 p.7: marks phase completion, deliverable handoff, external event, or go/no-go. No "false milestones" (routine WP completion, recurring events)
  • Completion criterion for each milestone is specific and verifiable (contains artifact/result + action + by whom)
  • Sum of durations (accounting for parallelism) ≤ total project duration. If not — recorded as issue
  • Duration unit is consistent throughout the plan (wd or wk) and follows the rule: ≤ 3 months → wd, > 3 months → wk
  • Each resource load ≤ 100% per period (or issue is recorded)
  • All agent assumptions listed in the Assumptions section
  • Document status =
    draft
  • File:
    project-plan.md
    listed in the header

6. Dependencies

Consumes (input):

  • project-charter.md
    (approved) — from skill
    generate-charter
  • Optional: duration estimates and team availability data from the user

Produces (output): project plan → consumed by skills (system-prompt-draft.md §7):

  • generate-risk-register
    (mode: detailed) — phase 2, Planning (parallel with comm-plan)
  • generate-comm-plan
    — phase 2, Planning (parallel with risk-register)
  • generate-resource-plan
    — phase 2 (Product 1, not MVP)
  • monitor-progress
    — phases 4–5 (Product 1)
  • generate-plan-fact-report
    — phase 6
  • coordinate-executors
    — phases 3, 5 (Product 1)
  • generate-checklist
    — phases 5, 6 (Product 1)

After the plan is approved, the user must upload

project-plan.md
to project knowledge so dependent skills can access it.


7. Example Invocation

User command:

Generate a project plan. The charter is approved and uploaded to knowledge. I don't have duration estimates for work packages — assess based on scope.

Agent response (after generation):

Project plan "[name]" generated based on: project charter (project-charter.md).

Assumptions:

  • Duration of all work packages estimated by the agent based on scope volume and team composition.
  • Team load distributed evenly (no availability data provided).
  • Phase priority: Development → Testing → Launch (standard order for IT projects).

Issues:

  • [Name]'s load exceeds 100% in May (WP-005 + WP-007 in parallel). Options: shift WP-007 to June or add a resource.

Required: approve, provide comments, or reject.

[plan text]


Changelog

DateVersionChange
2026-03-251.0Skill created. Algorithm: 14 steps. Hybrid duration estimation model. Resource map with fallback to charter data. Milestone definition criteria. Budget is optional
2026-03-261.1§2 p.4: added explicit WP counter — verify ≤20 after decomposition, consolidate adjacent packages if exceeded. §2 p.5: clarified behavior on date conflict — do NOT generate dates beyond end_date; mark affected WPs with ⚠ and require user decision
2026-03-291.2Translated to English. Added Language Detection block and bilingual triggers