Plan a structured software release cycle by defining strategy (calendar-based or feature-based), setting milestones with target dates, establishing feature freeze criteria, managing release candidates, defining go/no-go checklists, and documenting rollback plans. Produces a
RELEASE-PLAN.md artifact that guides the team from development through release.
When to Use
- Starting planning for a major or minor version release
- Transitioning from ad-hoc releases to a structured release cadence
- Coordinating a release across multiple teams or components
- Defining quality gates and release criteria for a regulated project
- Planning the first public release (v1.0.0) of a project
Inputs
- Required: Target version number (e.g., v2.0.0)
- Required: Desired release date or release window
- Required: List of planned features or scope (backlog, roadmap, or description)
- Optional: Team size and availability
- Optional: Release strategy preference (calendar-based or feature-based)
- Optional: Regulatory or compliance requirements affecting release
- Optional: Previous release velocity or cycle duration data
Procedure
Step 1: Determine Release Strategy
Choose between two primary strategies:
Calendar-based (time-boxed):
- Release on a fixed schedule (e.g., every 4 weeks, quarterly)
- Features that are not ready are deferred to the next release
- Predictable for users and downstream projects
- Best for: libraries, frameworks, tools with external consumers
Feature-based (scope-driven):
- Release when a defined set of features is complete
- Date adjusts to accommodate scope
- Risk of scope creep and indefinite delays
- Best for: internal tools, first releases, major rewrites
For most projects, a hybrid approach works well: set a target date with a defined scope, but allow a 1-2 week buffer. If scope is not met by the buffer deadline, defer remaining features.
Document the strategy choice with rationale.
Expected: Release strategy documented with rationale matching project context.
On failure: If the team cannot agree on a strategy, default to calendar-based with a feature-priority list. Time-boxing forces prioritization decisions.
Step 2: Define Milestones
Break the release cycle into phases with target dates:
## Release Plan: v2.0.0 ### Timeline | Phase | Start | End | Duration | Description | |---|---|---|---|---| | Development | 2026-02-17 | 2026-03-14 | 4 weeks | Active feature development | | Feature Freeze | 2026-03-15 | 2026-03-15 | 1 day | No new features merged after this date | | Stabilization | 2026-03-15 | 2026-03-21 | 1 week | Bug fixes, documentation, testing only | | RC1 | 2026-03-22 | 2026-03-22 | 1 day | First release candidate tagged | | RC Testing | 2026-03-22 | 2026-03-28 | 1 week | Community/team testing of RC | | RC2 (if needed) | 2026-03-29 | 2026-03-29 | 1 day | Second RC if critical issues found | | Go/No-Go | 2026-03-31 | 2026-03-31 | 1 day | Final decision meeting | | Release | 2026-04-01 | 2026-04-01 | 1 day | Tag, publish, announce |
Typical phase durations:
- Development: 50-70% of total cycle
- Stabilization: 15-25% of total cycle
- RC testing: 10-20% of total cycle
Expected: Milestone table with dates, durations, and descriptions for each phase.
On failure: If the timeline is too compressed (stabilization < 1 week), either extend the release date or reduce scope. Never skip stabilization.
Step 3: Set Feature Freeze Criteria
Define what "feature freeze" means for this release:
### Feature Freeze Criteria After feature freeze (2026-03-15): - **Allowed**: Bug fixes, test additions, documentation updates, dependency security patches - **Not allowed**: New features, API changes, refactoring, dependency upgrades (non-security) - **Exception process**: Feature freeze exceptions require written justification and approval from [release owner] ### Feature Priority List | Priority | Feature | Status | Owner | Notes | |---|---|---|---|---| | P0 (must) | New export format | In progress | [Name] | Blocks release | | P0 (must) | Security audit fixes | Not started | [Name] | Compliance requirement | | P1 (should) | Performance optimization | In progress | [Name] | Defer if not ready | | P2 (nice) | Dark mode support | Not started | [Name] | Defer to v2.1.0 if needed |
P0 features block the release. P1 features should be included if ready. P2 features are deferred without delay.
Expected: Feature freeze rules documented with exception process and prioritized feature list.
On failure: If P0 features are at risk of missing the freeze date, escalate immediately. Options: extend development phase, split the feature into a smaller deliverable, or defer to a point release (v2.0.1).
Step 4: Plan Release Candidate Process
Define how release candidates are produced and tested:
### Release Candidate Process 1. **RC1 Tag**: Tag from the stabilization branch after all P0 features merged and CI green ```bash git tag -a v2.0.0-rc.1 -m "Release candidate 1 for v2.0.0"
-
RC Distribution: Publish RC to staging/testing channel
- R:
install.packages("pkg", repos = "https://staging.r-universe.dev/user") - Node.js:
npm install pkg@next - Internal: Deploy to staging environment
- R:
-
RC Testing Period: 5-7 business days
- Run full test suite including integration tests
- Verify all P0 features work as documented
- Test upgrade path from previous version
- Check for regressions in existing functionality
-
RC Evaluation:
- No critical/high bugs: Proceed to release
- Critical bugs found: Fix, tag RC2, restart testing period
- More than 2 RCs needed: Revisit scope and timeline
-
RC2+ Tags: Only if critical issues found in previous RC
git tag -a v2.0.0-rc.2 -m "Release candidate 2 for v2.0.0"
**Expected:** RC process documented with tagging convention, distribution method, testing checklist, and escalation criteria. **On failure:** If the RC process is skipped (pressure to release), document the risk. Untested releases have higher rollback probability. ### Step 5: Define Go/No-Go Checklist Create the criteria that must be met before release approval: ```markdown ### Go/No-Go Checklist #### Must Pass (release blocked if any fail) - [ ] All CI checks passing on release branch - [ ] Zero critical bugs open against this version - [ ] Zero high-severity security vulnerabilities - [ ] All P0 features verified and documented - [ ] Changelog complete and reviewed - [ ] Upgrade path tested from previous version (v1.x -> v2.0.0) - [ ] License and attribution files up to date #### Should Pass (release proceeds with documented risk) - [ ] Zero high bugs open (non-critical) - [ ] All P1 features included - [ ] Performance benchmarks within acceptable range - [ ] Documentation reviewed and spell-checked - [ ] External dependencies at latest stable versions #### Decision - **Go**: All "Must Pass" items checked, majority of "Should Pass" items checked - **No-Go**: Any "Must Pass" item unchecked - **Conditional Go**: All "Must Pass" checked, significant "Should Pass" items unchecked — document accepted risks
Expected: Go/no-go checklist with clear pass/fail criteria and decision rules.
On failure: If the go/no-go meeting results in no-go, identify the blocking items, assign owners, set a new target date (typically 1-2 weeks later), and update the release plan.
Step 6: Document Rollback Plan
Define how to roll back if the release causes critical issues in production:
### Rollback Plan #### Rollback Triggers - Critical bug affecting >10% of users - Data corruption or loss - Security vulnerability introduced by the release - Breaking change not documented in changelog #### Rollback Procedure 1. **Revert package registry**: Unpublish or yank the release - R/CRAN: Contact CRAN maintainers (cannot self-unpublish) - npm: `npm unpublish pkg@2.0.0` (within 72 hours) - GitHub: Mark release as pre-release, publish point fix 2. **Communicate**: Notify users via GitHub issue, mailing list, or social channels - Template: "v2.0.0 has been rolled back due to [issue]. Please use v1.x.y until a fix is released." 3. **Fix forward**: Prefer a v2.0.1 patch release over a full rollback when possible 4. **Post-mortem**: Conduct a post-mortem within 48 hours of rollback to identify process gaps #### Point Release Policy - v2.0.1 for critical bug fixes within 1 week of release - v2.0.2 for additional fixes within 2 weeks - Patch releases do not require full RC cycle but must pass CI and critical test suite
Write the complete release plan to
RELEASE-PLAN.md or RELEASE-PLAN-v2.0.0.md.
Expected: Rollback plan documented with triggers, procedure, communication template, and point release policy. Complete RELEASE-PLAN.md written.
On failure: If rollback is not feasible (e.g., database migration already applied), document the forward-fix procedure instead. Every release should have a recovery path.
Validation
- Release strategy (calendar/feature/hybrid) documented with rationale
- Milestone table includes all phases with dates: development, freeze, stabilization, RC, release
- Feature freeze criteria defined with allowed/disallowed change types
- Feature priority list categorized (P0 must / P1 should / P2 nice)
- RC process documented: tagging convention, distribution, testing period, escalation
- Go/no-go checklist has clear "must pass" and "should pass" sections
- Rollback plan includes triggers, procedure, and communication template
- RELEASE-PLAN.md (or equivalent) file created and saved
- Timeline is realistic (stabilization is at least 15% of total cycle)
Common Pitfalls
- No stabilization phase: Going directly from development to release. Even a 3-day stabilization period catches issues that active development masks.
- Scope creep after freeze: Allowing "just one more feature" after feature freeze. Every post-freeze addition resets testing and introduces regression risk.
- Ignoring P0 risks: Not escalating early when a P0 feature is at risk. The earlier scope is adjusted, the less disruption to the timeline.
- Skipping RC for "small" releases: Even minor releases benefit from at least one RC. A day of RC testing is cheaper than a post-release hotfix.
- No rollback plan: Assuming the release will succeed. Every release plan should answer "what if this goes wrong?" before publishing.
- Calendar pressure overriding quality: Releasing on a date because it was promised, despite failing go/no-go criteria. A delayed release is a minor inconvenience; a broken release is a trust violation.
Related Skills
-- Determine the version number for the planned releaseapply-semantic-versioning
-- Maintain the changelog that feeds into release notesmanage-changelog
-- Sprint planning within the development phase of the release cycleplan-sprint
-- Project charter may define the release roadmap and success criteriadraft-project-charter
-- Track progress against release milestonesgenerate-status-report